Job 142
The scope of work for this project included extensive installation and rehabilitation of sanitary sewer and water infrastructure, along with associated system improvements, appurtenances, and surface restoration.
Site Work Solutions installed approximately 1,710 linear feet of 18-inch sewer piping, 380 linear feet of 12-inch sewer piping, 6,000 linear feet of 8-inch sewer piping, 4,000 linear feet of 6-inch sewer piping, and 5,100 linear feet of 4-inch sewer piping.
The project also included the installation of 34 new sanitary sewer manholes, 17 rod holes, 215 two-way cleanouts, 22 backcheck valves, 25 re-routed sewer laterals, and 10 re-plumbed laterals. Additional sewer-related work included associated appurtenances and abandonment of existing infrastructure as required.
Water system improvements included the installation of approximately 190 linear feet of 8-inch water piping, 760 linear feet of 6-inch water piping, and 125 linear feet of 1-inch water piping, along with two (2) new fire hydrants and one (1) combination air valve (CAV).
Following underground utility construction, approximately 105,000 square feet of roadway and disturbed surface areas were restored with chip seal. The completed project provided significant upgrades to the community’s water and wastewater infrastructure, improving system capacity, reliability, and long-term serviceability.