Job 142
The scope of work for this project consisted of installing approximately 1,710 LF of 18-inch, 380 LF of 12-inch, 6,000 LF of 8-inch, 4,000 LF of 6-inch and 5,100 LF of 4-inch sewer piping; 34 new manholes; 17 new rod holes; 215 two-way cleanouts; 22 backcheck valves; 25 re-routed laterals, 10 re-plumb laterals; 190 LF of 8-inch, 760 LF of 6-inch and 125 LF of 1-inch water piping; 2 fire hydrants; 1 CAV; 105,000 sq. ft. of chip seal restoration; appurtenances; and abandonments.