Job 163

Site Work Solutions performed underground utility, electrical conduit, and structural modifications within the substation yard and associated building areas.

Prior to excavation, an underground utility investigation was conducted using ground-penetrating radar (GPR) to identify existing utilities and help ensure safe excavation activities.

Two (2) 2-inch conduits were installed from the interior southwest corner of Building 3 underground to the interior southeast corner of Building 4. Two (2) 2-inch EMT conduits were then installed from the southeast corner of Building 4 to the southwest corner, with the conduits stubbed out through the building. All new conduit sections were interconnected to establish a continuous pathway from Building 3 to Building 4 and from Building 4 to the substation cable tray.

Weather-rated junction boxes were installed at conduit entry and exit points at the buildings. The conduit connection to the substation cable tray was completed through the open bottom of the cable tray using protective plastic as required. Following conduit installation, trenches were backfilled and asphalt surfaces were restored.

The existing stairs providing access to the mezzanine were removed and modified as necessary to accommodate a new west-to-east orientation along the north end of the mezzanine. Required modifications were made to the mezzanine structure to facilitate proper installation of the relocated stairs.

Additional work included relocating and replacing conduits, light fixtures, braces, penetrations, and other components as necessary to accommodate the stair installation. A new section of railing was also installed to close the opening in the mezzanine railing created by the removal and relocation of the existing stairs.

Specifications

Date Completed: Ongoing Project
City: Elverta
State: ca
Work Type/s: ,
PSC Code/s: --
Govt Type:
Award Amount: $134,984
Contracting Set Aside: